METHOD STATEMENT SETTING CONTAINER OFFICE

Mei 09, 2017

Key Plant and Tools Required:
- Mobil Crane 7 ton
- Webbing Sling 3inch
- Shackle @3/4

Key Materials Required:
- Stone - Wood
- Sand - Fence pole
- Cement - Steel Plate
- Concrete pipe - BRC

Other Essential Equipment:
- Barricade Tape


Specific Identified Residual Hazards: (or refer to the task specific risk assessment(s))
- Spinal cord injury when lifting up cause failure of body position
- Slip/fall when up/down the crane
- Sling broken/improper
- Crane nudging/bumping a worker/vehicle/heavy equipment
- Rigger fell from above over 1,8 m


Specific Staff Training Requirements:
- Certified rigger
- Certified crane operator
- Certified and inspected crane


Sequence of Operations:
(Specifying methods of
working, tools, materials and equipment utilized)
1. First, set the area for office container and logistic container, and set the pedestal made of coconut wood in the desired area.
2. Mobile crane will be positioned on the desired area
3. Trailer truck will come to the office are bring 2 sets of 20 feet container (office container and logistic container)
4. After both of mobile crane and trailer set in their position, lifting work can be started
5. Ensure the rigging activity following the rigging plan, certified rigger needed. For rigging material using four pieces of web sling 3”.
6. Lifting activity can be started, SWL procedures must be followed. In this lifting activity will use 6m boom from mobile crane.
7. Set both containers in the desired position.

1 komentar:

  1. Container Liners are one of the most innovative and efficient solutions for transporting bulk goods. They are primarily used for securing and protecting dry bulk materials during transit, ensuring that the contents of shipping containers remain safe from contamination, moisture, and damage. A liner bag container offers several advantages over traditional packaging methods, particularly for industries that handle large volumes of granular, powder, or liquid bulk products. In this article, we’ll explore the importance, advantages, and applications of container liners, and why they have become an essential part of modern shipping and logistics.

    BalasHapus

Cari Blog Ini

Arsip Blog

Laman

METHOD STATEMENT SETTING CONTAINER OFFICE

Key Plant and Tools Required: - Mobil Crane 7 ton - Webbing Sling 3inch - Shackle @3/4 Key Materials Required: - Stone - Wood ...

Diberdayakan oleh Blogger.