METHOD STATEMENT SETTING CONTAINER OFFICE
Key Plant and Tools Required:
- Mobil Crane 7 ton
- Webbing Sling 3inch
- Shackle @3/4
Key Materials Required:
- Stone - Wood
- Sand - Fence pole
- Cement - Steel Plate
- Concrete pipe - BRC
Other Essential Equipment:
- Barricade Tape
Specific Identified Residual Hazards: (or refer to the task specific risk assessment(s))
- Spinal cord injury when lifting up cause failure of body position
- Slip/fall when up/down the crane
- Sling broken/improper
- Crane nudging/bumping a worker/vehicle/heavy equipment
- Rigger fell from above over 1,8 m
Specific Staff Training Requirements:
- Certified rigger
- Certified crane operator
- Certified and inspected crane
Sequence of Operations:
(Specifying methods of
working, tools, materials and equipment utilized)
1. First, set the area for office container and logistic container, and set the pedestal made of coconut wood in the desired area.
2. Mobile crane will be positioned on the desired area
3. Trailer truck will come to the office are bring 2 sets of 20 feet container (office container and logistic container)
4. After both of mobile crane and trailer set in their position, lifting work can be started
5. Ensure the rigging activity following the rigging plan, certified rigger needed. For rigging material using four pieces of web sling 3”.
6. Lifting activity can be started, SWL procedures must be followed. In this lifting activity will use 6m boom from mobile crane.
7. Set both containers in the desired position.

Container Liners are one of the most innovative and efficient solutions for transporting bulk goods. They are primarily used for securing and protecting dry bulk materials during transit, ensuring that the contents of shipping containers remain safe from contamination, moisture, and damage. A liner bag container offers several advantages over traditional packaging methods, particularly for industries that handle large volumes of granular, powder, or liquid bulk products. In this article, we’ll explore the importance, advantages, and applications of container liners, and why they have become an essential part of modern shipping and logistics.
BalasHapusThe Jumbo bag plastic are heavy-duty, high-capacity packaging solutions made from woven polypropylene. Designed for transporting and storing bulk materials like grains, fertilizers, sand, and construction supplies, these bags offer excellent strength, tear resistance, and durability. Their lightweight yet sturdy design makes them a cost-effective, reusable, and eco-friendly choice for industrial and agricultural applications.
BalasHapusThe Tree guard net are protective enclosures designed to shield young trees from animals, harsh weather, and mechanical damage. Made from durable, UV-resistant plastic, they create a safe microclimate that promotes healthy growth while preventing bark damage and breakage. Lightweight, easy to install, and low-maintenance, plastic tree guards are ideal for agricultural, urban, and reforestation applications.
BalasHapusThe ABS plastic sheets are versatile, durable, and widely used in various industries due to their excellent impact resistance, toughness, and lightweight nature. Acrylonitrile Butadiene Styrene (ABS) is a thermoplastic known for combining the strength and rigidity of acrylonitrile and styrene with the toughness of polybutadiene rubber.
BalasHapusGreat article! The increasing demand for modular and mobile infrastructure really highlights how the construction and project management industries are evolving.
BalasHapusAt Guru Nanak Porta Cabin , we’ve been providing portable office containers like the one in your post — perfect for on-site offices. They’re quick to deploy, durable, and fully customizable based on project needs.
If anyone’s looking for reliable site office Container feel free to check out our work Office Container
Thanks again for the great insights.
This product is perfect for improving efficiency when handling a hard to close shipping container door in logistics operations.
BalasHapus